ActiveCampaign

Chicago, Illinois

PROJECT

52,000-sf tenant buildout of the 5th floor at 1 North Dearborn consists of offices with glass fronts; open office workstations; meeting rooms named with comic book themes; collaborations spaces; café and servery with exposed wood timbers; and reception area with decorative metal ceiling and significant branding. Additional features include new lighting, VAVs, and FPBs; updated carpeting over an existing raised floor; and a decorative concrete floor finish.

 

Executive Construction returned in 2019 to buildout the 4th floor to support ActiveCampaign’s growing Chicago staff. The expanded space of 52,000 sf features a massive interconnecting stair located behind the 5th floor reception that required extensive demolition, and erection of soundproofing partitions to protect staff during ongoing office operations. Stadium seating is featured on the stair, with two large projection screens and small stage at base of stairs for presentations and town hall meetings. Additional features include open workstations and glass-front meeting rooms to match 5th floor themes; phone rooms; wellness rooms; staff and visitor coffee bar; toilet rooms; huddle spaces; and a seminar space with theater seating, projection screens, and small pantry. Significant branding throughout includes custom carved “living wall” wood feature with geometric inlays for moss in both the seminar space and behind large presentation stage.

PROJECT MANAGER

Cushman & Wakefield

ARCHITECT

Eastlake Studio

ENGINEER

Kent Consulting Engineers

SERVICES

Preconstruction
General Contracting

SCHEDULE

Duration: 30 weeks (4th Floor); 15 weeks (5th Floor)
Completion: 4/20 (4th Floor); 8/17 (5th Floor)