Fortune 200 Company

DATA CENTER

Preconstruction and construction services for a new, 70,000-sf Tier III data center on a five acre site. Project components include a 35,000-sf data center; 17,000-sf of support spaces; 18,000-sf of disaster recovery; and 5,000-sf of exterior support. Features include one 500-ton chiller; twenty 30-ton Liebert air condition units (redundant DX cooling source); three 2000 kW generators; and two 1500 kVA paralleled UPS systems. Sitework encompasses a truck dock and parking for 120 cars; and the building structure consists of a steel frame with precast exterior panels and a hardened concrete roof.

 

Executive Construction provided extensive preconstruction services, including pre-ordering of all major electrical and HVAC equipment.